Back in QC11, I used ”Standard Report”, now, I don’t see them in QC12.53, can I re-enable them so I can create one?
Question ID: 107896
1
0

We just upgraded from QC11 recently and I am trying to create a Standard report from the Analysis view page in the Dashboard module.

On my old QC11 instance (still standing), I can see "Project Report" as a report type. In QC/ALM 12.53, I do not see Project Report, can it be enabled somehow to allow me to create and work with Project Reports (the old way)?

Marked as spam
Posted by (Questions: 91, Answers: 5)
Asked on October 17, 2017 4:35 pm
70 views
Answers (1)
1
Private answer

Yes, there is a site parameter (added by your Site Administrator) that can enable it:

**ENABLE_CREATE_STANDARD_REPORT**

Add parameter to list and set to ''Y''

Description: Determines whether Standard Reports should be included in the 'New Analysis Item' menu.
Default value: N Introduced in release: ALM 11.50

Marked as spam
Posted by (Questions: 4, Answers: 509)
Answered on October 17, 2017 4:38 pm
EyeOnTesting