Is there a way to configure a ALM-PC 11 Scenario test to stop after a fixed duration regardless of Vuser state?
Question ID: 104997
3
0

Is there a way to configure a ALM-PC 11 Scenario test to stop after a fixed duration regardless of Vuser state? Looks like Performance Center option is "Stop test when Scheduler ends AND Vusers are inactive". Any input will be great.

Marked as spam
Posted by (Questions: 17, Answers: 266)
Asked on May 1, 2013 5:14 pm
40 views
Answers (1)
4
Private answer

Just a thought; but, you could put a function call inside the script that will check the current time against the start time or clock time and have the script do an lr_abort at the desired time or desired elapse time. Just a matter of adding some code.

Marked as spam
Posted by (Questions: 4, Answers: 41)
Answered on July 18, 2013 6:26 pm
EyeOnTesting

Welcome back to "EyeOnTesting" brought to you by Orasi Software, Inc.

X
Scroll to Top