KPI Scorecard not generating with appropriate color coding
Question ID: 105470
0
0

WE have KPI set up to have the Planned for Passed Tests is 25% OK Above with % Warning Range 5. The actual for the week was 27% but the color code was Yellow instead of Green.
Why is it showing Yellow instead of Green for the Cell in the Scorecard table?

![alt text][1]

[1]: /storage/temp/189-2014-07-08_1310.png

Marked as spam
Posted by (Questions: 99, Answers: 7)
Asked on July 8, 2014 7:11 pm
37 views
Answers (1)
0
Private answer

On a scorecard with the ''demo'' project, I see 93% in yellow, and hovering shows ''Measured value 93 of 100, OK value >= 100%, Critical Value <= 90%. ![alt text][1] There was no unusual configuration of ''Passed Tests''. If you DRILL DOWN into the Yellow Cell, you should see the reason -- the color represents the TREND. On my Demo project, when drilling down, I see a ''tests executed over time'' cumulative chart with a Blue line showing the current ''tests executed'' value as it changes for the various days of data represented. On mine, the Blue line ends within the Yellow/Critical zone. ![alt text][2] So, this must represent the CURRENT state -- for mine, even though there were 93% executed (OK), since my current state (today) is in the Critical zone, it displays Yellow. [1]: /storage/temp/190-yellow-onscorecard.png [2]: /storage/temp/191-reason_its_yellow.png

Marked as spam
Posted by (Questions: 4, Answers: 509)
Answered on July 8, 2014 7:14 pm