Votes
Answers
Views
Question
0
1
26
asked 10 years ago by soapy-smith
updated 10 years ago by pt-barnum
WE have KPI set up to have the Planned for Passed Tests is 25% OK Above with % Warning Range 5. The actual for the week was 27% but the color code was Yellow instead of Green. Why is it showing Yellow instead of Green for the Cell in the Scorecard table? ![alt text][1] [1]: /storage/temp/189-2014-07...