We are trying to copy test cases back and forth from our dev instance of ALM to our production instance of ALM, currently we are getting the error: Failed to Paste Data

Our prod server is using ALM 12.01 Patch 0 and our Dev server is using ALM 12.01 Patch 3

Marked as spam
Posted by (Questions: 98, Answers: 0)
Asked on October 14, 2016 6:47 pm
185 views
Answers (1)
0
Private answer

Both of your ALM 12.01 servers will need to be at the same version to copy and paste between the two, I would recommend upgrading the prod server to patch 3.

Marked as spam
Posted by (Questions: 0, Answers: 364)
Answered on October 14, 2016 6:49 pm