How to move Test suite from Test Plan to Test Lab and test are in the exast same order as they are in Test Plan?
♥ 0 |
In ALM 11.0, when I use Select Tests in the Test Lab and pull a regression test suite from the Test Plan, the tests are not in the same order. They are in the order I want them in, in the Test Plan, but then when I run them one by one in the Test lab I will be running tests that need another test ran before that specific test was ran. I know I can go to Test Lab and select the Tests tab and then select Order Test Instances. This will allow me to do one by one manually. This is kind of difficult with 395 test cases. Is there some setting in ALM where it pulls all of the test cases in the same order they are in, in the Test Plan? Or does it always rearrange them when pulling them over to the Test Lab?
Marked as spam
|