Error when migrating QC10 project to QC11: PR_SMART_REPOSITORY_ENABLED
Question ID: 104999
1
0

I’m migrating a project from QC10 but am receiving an error when trying to Restore to my QC11 instance. The error says "The PR_SMART_REPOSITORY_ENABLED tag in the dbid.xml file of the project must be assigned the value of ‘N’." I’ve tried changing this but it doesn’t work. Any help?

Marked as spam
Posted by (Questions: 424, Answers: 91)
Asked on May 2, 2013 6:15 pm
29 views
Answers (1)
1
Private answer

I'm assuming you copied over the PR_SMART_REPOSITORY_ENABLED tag from an existing QC11 project. You do NOT want that PR_SMART_REPOSITORY_ENABLED tag as part of your dbid.xml for the pre-upgraded version 10 project before you Restore. This tag is added automatically by QC11 once it migrates the project's repository to the Smart Repository AFTER you upgrade the project.

Marked as spam
Posted by (Questions: 0, Answers: 771)
Answered on May 2, 2013 6:15 pm
0
That worked...I can now successfully restore the project. Now, on to my Verify/Repair/Upgrade!