Our company uses team foundation server (2015) as the company’s main application life cycle management and issue tracker. As the test department we have been working on QC alm for years and now we have to either completely move to TFS or in case we decide to keep working on ALm QC we have to sync with it.
We chose syncing using alm synchronizer (12.60).
Is there any risk that we have to consider? Meaning after sync is there any possibility that we face problems like syncing issues, losing data, incapability of syncing one of the endpoints in bidirectional mode, etc. ? We are worried about the problems that we might face in long term. Any Assistance or sharing experiences would be greatly appreciated.