Getting ”Project Corrupt” message at end of UPGRADE from Qc11 to 12.21, but it PASSED VERIFY and REPAIR
Question ID:
106372
♥ 0 |
We are trying to upgrade a QC11 project to QC12.21 (OK as far as the Install Guide says). We Restored the project, ran VERIFY and it says REPAIR will fix the problems, then we ran REPAIR and it says "successful". Then, we ran REPAIR. It looks like it makes some changes and runs it’s own verify, then makes more changes. it gets tot he end and says the project is "corrupt" — YIKES!!! How did it get corrupt between our manual run of VERIFY/REPAIR and when the UPGRADE ran VERIFY? It seems this would be a QC UPGRADE task issue not recognizing it’s own work-in-progress, what can be done?
Marked as spam
|
Answers (1)