HP Synchronizer – missing Requirement Target CYCLE?
Question ID: 105944
0
0

We are trying to configure the Sync QC requirements to TFS Backlog, but I cannot find the "Target Cycle" field in the Field mapping list from QC for the link. The Target Release is present, but there is no Target Cycle.

I have tried to refresh Schema, Cycle services on the HP-sync server, reboot, doesn’t help this field to appear.

Marked as spam
Posted by (Questions: 193, Answers: 14)
Asked on February 20, 2015 9:24 pm
38 views
Answers (1)
0
Private answer

This is a ''quirk'' of Synchronizer -- it actually says in the User Guide that the only release/cycle fields used by Requirements synchronization is ''Target Release''.

Marked as spam
Posted by (Questions: 4, Answers: 509)
Answered on February 20, 2015 9:26 pm
0
I should have looked in the Manual, D'oh!
( at February 20, 2015 10:37 pm)
EyeOnTesting

Welcome back to "EyeOnTesting" brought to you by Orasi Software, Inc.

X
Scroll to Top